Operations >
Project Management
COVERS ALL MAJOR EXAM BOARDS
Teaching Business
Network Analysis
A clear guide to network analysis and critical path analysis, covering project activities, dependencies, network diagrams, EST, LFT, float, critical path, minimum project duration and project management decisions.
10
Created by an experienced Head of Business and examiner
AQA | Edexcel | Cambridge | Eduqas | WJEC | OCR | GCSE
KEY POINTS
Network analysis is a project management tool used to plan complex projects.
Critical Path Analysis, or CPA, uses a network diagram to show activities, timings and dependencies.
Activities are the tasks that must be completed during a project.
Dependencies show which tasks must be completed before others can begin.
Nodes show points in the project where activities start or finish.
The critical path is the sequence of activities that determines the minimum project duration.
Activities on the critical path have no float, so delays to these activities delay the whole project.
Float shows how long an activity can be delayed without delaying the overall project.
EST means Earliest Start Time and LFT means Latest Finish Time.
CPA can help managers plan resources, monitor progress and identify activities that need close control.
CPA depends on accurate time estimates and may be less useful if projects are uncertain or change quickly.
Strong exam answers use the network data and then judge whether CPA is useful in the specific project context.
KEY DEFINITION
Network analysis
Network analysis is a project management technique that uses a diagram of activities, timings and dependencies to identify the critical path, project duration and float.
Main Explanation
Network analysis is a project management technique used to plan and control complex projects. It is often linked to Critical Path Analysis, or CPA. The technique helps managers break a project into separate activities, estimate how long each activity will take and identify which activities depend on others being completed first.
A network diagram shows the order in which activities must happen. For example, a business may need to complete a site survey before construction work begins, or install equipment before staff training can take place. This makes network analysis useful for projects where timing, sequencing and resource planning are important.
Activities are the tasks that make up the project. Each activity has a duration, such as three days, two weeks or four months. The diagram also shows dependencies. A dependency exists when one activity cannot start until another activity has been completed.
Nodes are points in the network where activities start or finish. Some network diagrams also use dummy activities. These do not take time, but they show a dependency clearly where one activity must wait for another before continuing.
A key aim of network analysis is to identify the critical path. The critical path is the longest sequence of dependent activities through the project. It determines the minimum time needed to complete the whole project. If any activity on the critical path is delayed, the whole project will be delayed unless managers take corrective action.
Network analysis also uses Earliest Start Time, or EST, and Latest Finish Time, or LFT. EST shows the earliest point at which an activity can begin. LFT shows the latest point at which an activity can finish without delaying the whole project.
Float is another important part of network analysis. Float shows how long an activity can be delayed without delaying the completion of the project. Total float is commonly calculated using the formula: Latest Finish Time minus activity duration minus Earliest Start Time. Activities with no float are usually on the critical path.
Free float may also be used in some specifications. Free float shows how long an activity can be delayed without delaying the start of the next activity. This can be useful where managers need to understand whether a delay affects the next stage of the project, even if it does not delay the whole project.
Network analysis can help managers plan resources. If they know which activities are critical, they can prioritise labour, equipment, materials or contractors for those activities. Activities with float may allow managers to move resources elsewhere without delaying the overall project.
CPA can also improve monitoring. Managers can compare actual progress with the planned network and identify where delays are most serious. This is useful in construction, product launches, store openings, IT upgrades, events and other time-sensitive projects.
However, network analysis has limitations. It depends on accurate estimates of activity durations and dependencies. If managers underestimate how long tasks will take, the network may give a false sense of certainty. Unexpected problems, supplier delays, staff shortages or weather disruption may make the original plan less reliable.
CPA can also focus attention on time rather than quality, cost or flexibility. Completing a project quickly is not always the same as completing it well. A business may need to balance speed against safety, quality, customer experience and budget control.
Overall, network analysis is useful when a project has clear activities, timings and dependencies. It is most valuable when managers use it to guide decisions, monitor progress and respond to delays, rather than treating the diagram as a guaranteed prediction.
✎ EXAMINER TIP
When answering questions on network analysis, use the numbers from the diagram. Identify the critical path, project duration and float, then explain what this means for project management decisions.
KEY FORMULAS(s)
Profit and Profitability Formulas
These key formulas help you calculate different profit measures and profitability ratios used in business.
Gross Profit
Gross profit = Revenue − Cost of sales
The profit made after deducting direct costs.
!
Remember: profit shows how much money has been made, while profitability shows how efficiently revenue is being turned into profit.
DATA TABLE
Income Statement for North Coast Coffee Ltd
This statement shows how revenue is converted into gross profit, operating profit and net profit.
Revenue
£250,000
Output
Fixed Costs
Variable Costs
Total Costs
Revenue
Profit / Loss
0 candles £1,200 £0 £1,200 £0 -£1,200
Net profit is the final profit remaining after all costs and expenses have been deducted from revenue.
Critical Path Analysis: Worked Example

Create a professional 900px × 600px landscape infographic for an A Level Business topic page titled “Network Analysis: Key Elements”. Use a modern, sleek and accessible classroom design on a plain white background. Keep it less wordy and highly visual. Show a clean network diagram with labelled elements: Activities, Nodes, Dependencies, Earliest Start Time (EST), Latest Finish Time (LFT), Total Float and Critical Path. Use a simple project example, such as a store refit, but no real company names. Highlight the critical path in a bold line and show non-critical activities with light lines. Add one concise note: “Critical activities have no float, so delays delay the project.” Use large readable labels, clear spacing and generic icons. No logos, no real businesses, no branded products.
WORKED EXAMPLE
Worked Example: North Coast Coffee
How many coffees must be sold to break even?
Fixed Costs
£1,800
equity + long-term debt
Break-even output = Fixed costs ÷ Contribution per unit
Contribution per unit = Selling price − Variable cost
£3.50 − £1.10 = £2.40
1
Step 1: Calculate contribution
£3.50 − £1.10 = £2.40
Contribution per unit is the amount each coffee contributes towards fixed costs.
BREAK-EVEN OUTPUT:
750 coffees per month
EXAM TIP
Always explain what the number means for the business. Do not just calculate the break-even point.

Network Analysis: Key Elements

This diagram shows the main elements of network analysis, including activities, nodes, dependencies, EST, LFT, float and the critical path.
APPLICATION
Balfour Beatty
Balfour Beatty provides a useful real-world context for network analysis because large construction and infrastructure projects involve many linked activities, contractors, resources and deadlines.
For a business like Balfour Beatty, a project may involve site surveys, design work, planning approval, supplier coordination, materials delivery, construction phases, safety checks and final handover. Some activities must happen in sequence, while others may be completed at the same time.
Network analysis could help project managers identify the critical path. This would show the sequence of activities that determines the shortest possible completion time. If a critical activity, such as foundation work or electrical installation, is delayed, the whole project may be delayed.
Float would also be useful. Activities with float may be delayed slightly without delaying the whole project, so managers may be able to move labour, equipment or contractors towards activities that are more urgent. This can improve resource planning and reduce the risk of costly delays.
CPA could also help with monitoring. Project managers could compare actual progress with the network diagram and identify where problems are most serious. This may support better communication with clients, subcontractors and suppliers.
However, construction and infrastructure projects are often uncertain. Weather, planning delays, supplier problems, health and safety issues or unexpected site conditions may make original time estimates inaccurate. This means the network diagram would need to be updated regularly.
Overall, Balfour Beatty shows why network analysis can be valuable for complex projects where timing and dependencies matter. The key judgement is whether the activity estimates are reliable enough for CPA to support better project management decisions.

This independent educational case study is not affiliated with, endorsed by or sponsored by Greggs plc. Any financial figures used alongside this example should be treated as simplified or hypothetical estimates created for teaching purposes.
_edited.png)
ANALYSIS
EXAM FOCUS
Analysis questions require you to examine a business concept or issue in detail, breaking it down into its component parts. You should explain how and why something happens and consider its impact on the business.
How to Approach Analysis Questions
1
Identify the key issue or concept
2
Break it down
3
Explain how and why
4
Reach a reasoned conclusion
Read the question carefully and highlight the focus of the analysis.
Consider the different factors, causes or impacts related to the issue.
Provide clear explanations using business terms and links points to context.
Evaluate the overall implications for the business.
Example Analysis Question
North Coast Coffee is considering using break-even analysis before opening a second café.
Advantages
• Sales forecasts may be inaccurate.
• Assumes costs and revenue remain constant.
• External factors may reduce reliability.
• Ignores qualitative business factors.
Disadvantages
• Sales forecasts may be inaccurate.
• Assumes costs and revenue remain constant.
• External factors may reduce reliability.
• Ignores qualitative business factors.
Key Exam Tip
If you find it difficult to expand your answer and show the type of depth that an examiner is looking for in a top response, consider using the 'so what' approach.
Tesco carry out market research - so what? - this allows them to better understand customer needs - so what? as a result Tesco can provide goods more likely to sell - so what? - this will increase Tesco profit and ensure higher levels of customer satisfaction - so what? this means that customers are likely to become more loyal to Tesco.

Avoid These Exam Traps
Students often lose marks on calculation and analysis questions by making these mistakes. Watch out for them in your exam!
1
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.

Tip:
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.
2
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.

Tip:
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.
3
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.

Tip:
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.
Be precise. Read the question carefully. Show your working.
Small mistakes can cost big marks.
EXAM PRACTICE
Practice Question
Apply your knowledge of profit and profitability to answer this exam-style question.
1
MINI CASE STUDY
North Coast Coffee Ltd is a premium coffee business which sells freshly roasted coffee beans through its online store and a small chain of independent cafés. The business has experienced strong sales growth due to increasing demand for high-quality speciality coffee products.
The business generates annual revenue of £250,000. Its cost of sales, including coffee beans, packaging and direct production costs, totals £100,000. North Coast Coffee Ltd also faces operating expenses of £80,000, including marketing, employee wages, rent and administration costs. In addition, the business pays £20,000 in interest and taxation each year.
The owner, Mia Thompson, is reviewing the company’s profitability because rising wage costs and increased competition in the premium coffee market have started to place pressure on operating profit margins. She is considering increasing prices slightly in order to protect profitability while still maintaining customer demand.
.jpg)
2
EXAM QUESTION
Analyse the possible reasons for BrightBite’s falling profit margins and evaluate strategies it could use to improve profitability.
3
HOW TO ANSWER
P
Point
E
Explain
A
Apply
C
Consequence
H
However...
4
MODEL ANSWER
P
Point
Increasing prices could improve the profitability of North Coast Coffee Ltd because each sale would generate a larger amount of revenue and potentially increase profit margins.
5
EXAMINER TIP
For full marks, make sure you analyse causes rather than just listing them, and evaluate realistic strategies with clear judgement. THINK: Which strategy would have the biggest impact and why?
CALCULATOR
THIS TOPIC · POWERPOINT RESOURCE
Network Analysis
CHOOSE YOUR EXAM BOARD:
Product Title
Instant download — school site licence included
-
Fully editable PowerPoint lesson
-
Relevant activities and practice questions
-
School site licence — share with your department
Helvetica Light is an easy-to-read font, with tall and narrow letters, that works well on almost every site.

£3.00
RELATED TOPICS
Continue Learning
Build your understanding by exploring other topics that connect closely with this one.

Profit and Profitability
Learn how to calculate profit and analyse profitability to measure the financial performance of a business.